There is no single 2.5-metre rule for everything
Height alone does not decide whether every event structure needs the same report. In the FEHD public entertainment licence guide, examples of extensive temporary structures that may require structural justification include a self-standing speaker or lighting tower exceeding 2.5 metres. Other examples have different thresholds.
The guide lists, for example, different heights for indoor and outdoor exhibition booths, and also includes suspended lighting truss by weight. These are examples in a particular licensing context, not a universal pass or automatic exemption below a given height.
Ask the right people early
Send the venue and the appropriate authorised person or registered structural engineer the location, dimensions, drawings, loads, connections, anchoring and programme. Outdoor exposure, ground conditions, nearby structures, rigging and audience access can change the assessment.
Confirm whether the activity requires a Temporary Places of Public Entertainment Licence and what documents, independent checking, supervision or certification are required for the actual installation. Venue rules or contract conditions can add requirements.
Keep the design and the built setup aligned
Do not assume a generic “IC report” covers every event. Agree who designs, who checks independently if required, who supervises erection and who signs the relevant completion documents. Record any changes and obtain approval before building.
The Buildings Department has a specific reuse process for some previously accepted structures under stated conditions. Check current guidance and obtain project-specific professional advice before installation.